Fort Peck Powerhouse 1 Cubicle Room 15kV Switchgear Replacement Project
SAM.GOV
Due: October 7, 2025 at 05:00 PM UTC
Active
Solicitation Source Url

Summary

The Fort Peck Powerhouse 1 Cubicle Room 15kV Switchgear Replacement Project involves the replacement of existing 15kV class breakers and associated equipment at the Fort Peck power plant. This project requires the removal of 10 breaker cubicles and the installation of 5 new breakers along with additional outdoor rated breakers in the switchyard. The work includes extensive electrical infrastructure upgrades, such as new bus systems, control modifications, and the installation of new reactor banks. Contractors with experience in power and communication line construction, particularly those familiar with high-voltage systems and tight project timelines, should consider bidding on this opportunity.
Description

UPDATE:  Amendment 0002 was issued on 6 August 2025.  Please see two (2) corresponding documents and updated proposal due date. 

UPDATE: The Contractor Sign-in Sheet for the Site Visit held on 5 August 2025 has been posted in the attachments. 

UPDATE:  Ame

Entities
DOD
Department of Defense
DOTA
Department of the Army
NAICS
237130
Set Aside
None
Place of Performance
Fort Peck , Montana 59223
Point of Contact
Full Name Email Phone Type
Margarette Wolfe [email protected] primary
Daniel D. Monahan [email protected] secondary
Attachments
  • Pre-Solicitation+Notice+W9128F25RA008+Fort+Peck+15kV+Switchgear+Upgrade.pdf
  • UPDATED_Pre-Solicitation+Notice+W9128F25RA008+Fort+Peck+15kV+Switchgear+Upgrade.pdf
  • 05-+FP+Cubicle+Room+15kV+Switchgear+Contract+Drawings_Final_2_of_5.pdf
  • 05-+FP+Cubicle+Room+15kV+Switchgear+Contract+Drawings_Final_4_of_5.pdf
  • 05-+FP+Cubicle+Room+15kV+Switchgear+Contract+Drawings_Final_5_of_5.pdf
  • 05-+FP+Cubicle+Room+15kV+Switchgear+Contract+Drawings_Final_1_of_5.pdf
  • 02-Div+00+22+00_FP+PH1+15kV+Switchgear.pdf
  • 03-+DBA+WD+MT20250076+18+July+2025.pdf
  • 01-Solicitation+-+W9128F25RA008+FP+PH1+15kV+Switchgear+Upgrade.pdf
  • 06-+W9128F25RA008+FP+PH1+Cubicle+Room+Switchgear+Upgrade+Specs.pdf
  • 05-+FP+Cubicle+Room+15kV+Switchgear+Contract+Drawings_Final_3_of_5.pdf
  • 04-+Fort+Peck+Cubicle+Room+15kV+Switchgear+Reference+Drawings_Final+Submittal.pdf
  • Amend+0001_W9128F25RA0080001+SF+30_FP+PH1+Switchgear.pdf
  • Amend+0001_W9128F25RA0080001_FP+PH1+Switchgear.pdf
  • Amend+0001_Div+00+22+00_FP+PH1+15kV+Switchgear_%28Clean%29.pdf
  • Amend+0001_Div+00+22+00_FP+PH1+15kV+Switchgear_%28Redlined%29.pdf
  • Site+Visit_KTR+SignIn+Sheet_5+Aug+2025_FP+PH1+Cubile+Room+Switchgear.pdf
  • Amend+0002_W9128F25RA0080002_FP+PH1+Switchgear.pdf
  • Amend+0002_W9128F25RA0080002+SF+30_FP+PH1+Switchgear.pdf