P-1238, CONSTRUCTION OF GRID STABILITY AND RESILIENCY 10 MW, BATTERY ENERGY STORAGE SYSTEMS, MARINE CORPS AIR GROUND COMBAT CENTER (MCAGCC), TWENTYNINE PALMS, CA
SAM.GOV
Due: June 3, 2025 at 09:00 PM UTC
In-Active Solicitation Source Url

Summary

The opportunity P-1238 involves the construction of a 10 MW Battery Energy Storage System at the Marine Corps Air Ground Combat Center (MCAGCC) in Twentynine Palms, California. This project aims to enhance grid stability and resiliency through the installation of various battery energy storage systems across multiple buildings. Contractors with experience in design-build projects, particularly those specializing in energy systems and construction within military or government contexts, are encouraged to bid on this solicitation. The project is significant in its scope and requires a contractor capable of managing complex construction tasks while adhering to strict safety and regulatory standards.
Entities
DOD
Department of Defense
DOTN
Department of the Navy
NAICS
237130
Set Aside
None
Place of Performance
Twentynine Palms , California 92277
Point of Contact
Full Name Email Phone Type
Kathryn Cranford [email protected] 6197054644 primary
Jaime Flores [email protected] 6197054873 secondary
Attachments
  • Phase+Two+Enclosure+3_P1238_Blank_OfferSchedule_Revised.xlsx
  • N6247324R5227_Amendment+0009_SF30.pdf
  • EXHIBIT+D_5227.pdf
  • WD+CA20240026-09-06-2024.pdf
  • N6247324R5227_Amendment+0008.pdf
  • AMENDMENT+0004+Opening+Discussions.pdf
  • N6247324R5227_Amendment+0006.pdf
  • EXHIBIT+A_5227.pdf
  • Phase+Two+Enclosure+4+-+P1238_RFI+Submission+Form.xlsx
  • EXHIBIT+E_P1238_Historical+Small+Business+Utilization.pdf
  • AMENDMENT+0001_P1238_24R5227_FINAL.pdf
  • EXHIBIT+F_+5227.pdf
  • RFI+RESPONSES_+N6247322R5227_02MAY24.xlsx
  • P1238_N6247322R5227_RFI_Submission+-+Non-Amendment+Responses_08MAY25.xlsx
  • Phase+Two+Enclosure+1+-+P1238_RFP+Part+1_Revision+2_02APR2025.pdf
  • N6247324R5227+Amendment+0007.pdf
  • RFI_RESPONSES_N6247322R5227_16MAY24_FINAL.xlsx
  • AMENDMENT+0002_24R5227_FINAL.pdf
  • Phase+Two+Enclosure+1+-+P1238_RFP+Part+1_Revised+01APR25.pdf
  • Phase+Two+Enclosure+5+-+P1238_Wage+Determination+CA20250017.pdf
  • Phase+Two+Enclosure+1+-+P1238_RFP+Part+1.pdf
  • Revised+Standard+Form+%28SF%29+1442_P1238_N6247324R5227.pdf
  • Phase+Two+Enclosure+3+-+P1238_Blank_OfferSchedule.xlsx
  • EXHIBIT+E_5227.pdf
  • AMENDMENT+0005+Close+Discussions+and+Request+FRPs.pdf
  • Amendment+0003.pdf
  • EXHIBIT+B_5227.pdf
  • Phase+Two+Enclosure+1_P1238_RFP+Part+1_Revised.pdf
  • EXHIBIT+C_5227.pdf
  • P1238_RFI+Submission+Form_Responses_17APR2025.xlsx
  • RFI+FORM+N6247322R5227.xlsx
  • EXHIBIT+B_Construction+Design+Controls+System+Experience+Project+Data+Sheet.pdf
  • AMENDMENT+0002_EXHIBITS_ATTACHMENTS_24RF5227.zip
  • N6247324R5227_FINAL_22APR+24.pdf