TINKER AFB 2-STEP COMPETITIVE 8(a) WWYK180061 REPAIR HVAC SYSTEM, B3707
SAM.GOV
Due: October 8, 2025 at 07:00 PM UTC
In-Active Solicitation SBA Source Url

Summary

The opportunity at Tinker Air Force Base involves a two-step competitive solicitation for the repair of the HVAC system in Building 3707. This project is specifically set aside for 8(a) construction contractors that are small businesses and have a physical office located in Oklahoma. The work will require contractors to attend a mandatory site visit to assess the project scope and requirements, which is a prerequisite for submitting a proposal. The project includes various technical specifications related to HVAC systems, including commissioning, vibration control, and safety measures, making it essential for bidders to have relevant experience and expertise in HVAC installations and repairs. Contractors interested in this opportunity should be familiar with federal contracting processes and possess the necessary qualifications to meet the technical demands outlined in the solicitation documents.
Description

Only the GCs that submitted a previous Technically Acceptable technical proposal will be able to continue forward to the award.

Updated 28 October 2025

The Bid Opening took place on 28 October 2025 at 10:30am.

The Apparent Low Bidder is Native Star

Entities
DOD
Department of War
DOTAF
Department of the Air Force
NAICS
236220
Set Aside
SBA : Total Small Business Set-Aside (FAR 19.5)
Place of Performance
S Coffeyville , Oklahoma 73145
Point of Contact
Full Name Email Phone Type
Stephen Palmer [email protected] 4057394182 primary
Brody Corbett [email protected] 4053175767 secondary
Attachments
  • 00+80+05.pdf
  • 32+01+17.62.docx
  • 23+08+00.pdf
  • 10+22+13.pdf
  • 32+17+23.pdf
  • tinkerafb_INRMP.pdf
  • USB-010874_TAFB+TO3+B3707_HW_RevC_Redlines_04302018.pdf
  • 23+05+48.00+40.pdf
  • 07+53+23.pdf
  • 28+31+33.00+10.pdf
  • 23+05+15.pdf
  • dafi21-101.pdf
  • 06+41+16.00+10.pdf
  • 23+65+00.docx
  • 07+52+00.pdf
  • 32+12+15.docx
  • 08+51+23.pdf
  • 32+13+73.pdf
  • TAFB_SOP_outages_v2.pdf
  • 32+01+22.pdf
  • TABLE+OF+CONTENTS_no+Anno.docx
  • 32+16+13.pdf
  • 23+57+10.pdf
  • 05+12+00.pdf
  • afman40-201.pdf
  • 10+14+00.10.pdf
  • 2023+TAFB+FIRE+PROTECTION+STANDARD.pdf
  • 32+17+23.docx
  • UMRL.pdf
  • 07+51+13.pdf
  • Solicitation+-+FA813725R0029.pdf
  • 07+42+13.pdf
  • GEOWEB.pdf
  • 07+31+13.pdf
  • 07+24+00.pdf
  • 08+11+16.pdf
  • afi91-202_afmcsup.pdf
  • 32+16+13.docx
  • Wage+Determination.txt
  • 180061_Submittal+Register_v4.pdf
  • afman32-7003.pdf
  • 23+25+00.docx
  • afi48-104.pdf
  • 26+56+00.pdf
  • 32+01+17.docx
  • 26+05+48.00+10.pdf
  • 31+00+00.pdf
  • 26+51+00.pdf
  • 007200_Attch+7b_Monthly+Hazardous+Usage+Report.pdf
  • 2025+TAFB+Electrical+Standards+-+Final.pdf
  • 04+20+00.pdf
  • 007000_Attch+1_TAFB+Outage+Request+Form.pdf
  • 09+68+00.pdf
  • B3707+CX+Report.docx
  • Section+M+-+Evaluation+Factors+for+Award.pdf
  • 32+12+10.2.pdf
  • 26+20+00.pdf
  • 23+01+30.41.pdf
  • 26+28+01.00+10.pdf
  • 00+70+00+%28wo_markup%29.pdf
  • 01+33+00.pdf
  • 32+12+15.pdf
  • 23+31+13.00+40.pdf
  • ATT9_180061_SOW_v3_Rev_8A.pdf
  • 26+00+00.00+20.pdf
  • ufc_3_260_04_2018.pdf
  • dodio-2000.16v1_afi10-245-o.pdf
  • SOW+Att+02a_Controlled+Area+Training.pptx
  • 02+41+00.pdf
  • 32+01+17.62.pdf
  • 32+12+10.2.docx
  • 01+45+00.00+10+%28wo_markup%29.pdf
  • dafi13-213_tinkerafbsup.pdf
  • 08+36+13.pdf
  • 08+56+53.pdf
  • 01+78+23+%28wo_markup%29.pdf
  • 01+42+00.pdf
  • 07+41+13.pdf
  • EMS+General+Awareness+Training+for+Contractors+Aug+2018.pptx
  • 017800_Attch+2_DD1354+Checklist.docx
  • 08+34+19.10+20.pdf
  • 23+34+23.00+40.pdf
  • 23+05+93.pdf
  • 32+13+14.pdf
  • 32+92+19.docx
  • ufc_3_535_01_2017_c4.pdf
  • 23+81+00.docx
  • 23+35+00.docx
  • 31+23+15.docx
  • 23+07+00.pdf
  • 32+11+29.pdf
  • 32+84+24.pdf
  • 31+23+15.pdf
  • afman48-148.pdf
  • 09+51+00.pdf
  • 07+92+00.pdf
  • tinkerafb_INRMP_App+E.pdf
  • 23+11+25.pdf
  • 000_TABLE+OF+CONTENTS.pdf
  • 01+78+00.pdf
  • DACA56-89-C0017.pdf
  • 23+09+23.01.pdf
  • 32+11+11.pdf
  • 28+31+00.00+10.pdf
  • USB-010874_B3707+Final+O+and+M.pdf
  • 33+11+00.pdf
  • 00+71+00.pdf
  • 32+92+23.docx
  • 05+40+00.pdf
  • 08+33+23.pdf
  • tinkerafbi21-100.pdf
  • 32+92+19.pdf
  • 013300_Attch1_TAFBF3000.pdf
  • 23+82+01.pdf
  • 10+21+13.pdf
  • 32+13+74.docx
  • 23+81+00.pdf
  • 23+03+00.docx
  • tinkerafb_INRMP_App+G.pdf
  • 23+64+10.docx
  • 23+82+23.00+40.pdf
  • SOW+Att+01_Appointment+of+Security+Representative+Template+496.docx
  • EM_385-1-1.pdf
  • 33+40+00.pdf
  • 10+26+00.pdf
  • 01+42+00+%28wo_markup%29.pdf
  • 23+81+23.pdf
  • 950104-M1.pdf
  • dafi21-101_afmcsup_afmcgm2023-01.pdf
  • WWYK180061+-+Pre-Bid+RFI+ResponseCOR+GK.pdf
  • 32+01+22.docx
  • 007200_Attch+9_EMS+Awareness+Training.pdf
  • 23+03+00.pdf
  • 05+30+00.pdf
  • 1995-HVAC-Renov-M1.pdf
  • 09+30+10.pdf
  • 21+13+17.docx
  • 07+42+63.pdf
  • 31+00+00.docx
  • 28+31+64.00+10.pdf
  • 32+11+11.docx
  • 2008-HVAC-Renov.pdf
  • 000_TABLE+OF+CONTENTS+%28wo_markup%29.pdf
  • 2020+TAFB+Facility+Standard.pdf
  • dafi13-213.pdf
  • DACA56-89-C0017-AB-1.pdf
  • 32+01+14.docx
  • 26+42+14.00+10.pdf
  • 23+52+00.pdf
  • 32+01+18.docx
  • 32+01+19.pdf
  • 26+41+00.pdf
  • 1995-HVAC-Renov.pdf
  • 01+78+23.pdf
  • 07+60+00.pdf
  • 03+20+00.00+10.pdf
  • 23+57+10.docx
  • 31+23+06.docx
  • 31+23+16.pdf
  • 26+08+00.pdf
  • 1990-OrigConst-Fire.pdf
  • 00+72+00+%28wo+markup%29.pdf
  • 23+64+10.pdf
  • 23+65+00.pdf
  • 23+70+03.docx
  • 01+32+16.00+20.pdf
  • 08+71+00.pdf
  • 32+13+11.pdf
  • ufc_3_260_01_2019_c1.pdf
  • 180061_Submittal+Register_v4.xlsx
  • 08+52+00.pdf
  • 05+05+23.16.pdf
  • 32+13+11.docx
  • 03+11+13.00+10.pdf
  • 09+72+00.pdf
  • dafi91-202.pdf
  • 1990-OrigConst.pdf
  • SOW+Att+02c_Controlled+Area+Training+-+Certificate.pdf
  • 08+51+13.pdf
  • 07+14+00.pdf
  • 01+33+16.00+10.pdf
  • 32+01+18.pdf
  • 1990-OrigConst-Controls.pdf
  • 23+00+00.pdf
  • 01+45+00.00+10.pdf
  • 09+22+00.pdf
  • 06+20+00.pdf
  • 07+62+13.pdf
  • 01+33+16.00+10+%28wo_markup%29.pdf
  • 10+44+16.pdf
  • 23+82+46.00+40.pdf
  • 08+41+13.pdf
  • ERDCITL_TR12-1_r2.pdf
  • ERDCITL_TR12-6_r6.pdf
  • 23+64+26.pdf
  • 2020+TAFB+Mechanical+Standard.pdf
  • 07+22+00.pdf
  • 32+01+13.docx
  • ATT3_180061_RMDF_CO-Signed.pdf
  • 26+32+14.00+10.pdf
  • 21+13+13.pdf
  • 08+81+00.pdf
  • 01+33+00+%28wo_markup%29.pdf
  • 32+01+14.pdf
  • 26+23+00.pdf
  • 26+56+20.00+10.pdf
  • 31+23+06.pdf
  • 10+28+13.pdf
  • 08+14+00.pdf
  • 03+30+00.pdf
  • 33+71+02.pdf
  • 32+01+19.docx
  • 22+05+48.00+20.pdf
  • 017800_Attch+1_DD1354.pdf
  • 09+90+00.pdf
  • 4+EAL+List+-+BLANK+to+Contractors.xlsx
  • 32+13+73.docx
  • 26+05+00.00+40.pdf
  • 32+01+17.pdf
  • 00+70+00.pdf
  • 01+50+00+%28wo_markup%29.pdf
  • 23+35+00.pdf
  • 23+23+00.pdf
  • 23+52+00.docx
  • 26+29+23.pdf
  • 32+11+23.pdf
  • 007100_Attch+1_Airfield+Construction+Waiver.pdf
  • 23+82+43.00+40.pdf
  • dafman91-203.pdf
  • 21+13+13.docx
  • 13+34+19.pdf
  • 007200_Attch+7a_AF3952.pdf
  • 23+82+16.00+40.pdf
  • 26+36+00.00+10.pdf
  • 07+72+20.pdf
  • 07+61+14.00+20.pdf
  • ufc_3_601_02_2021.pdf
  • 32+13+74.pdf
  • 33+40+00.docx
  • 05+21+00.pdf
  • 32+11+23.docx
  • 23+54+16+.pdf
  • 05+50+13.pdf
  • 13+48+00.pdf
  • 10+14+00.20.pdf
  • 01+50+00.pdf
  • 00+80+00.pdf
  • 23+81+23.docx
  • 000_TABLE+OF+CONTENTS+%282%29.pdf
  • 03+62+16.pdf
  • 00+80+00+%28wo_markup%29.pdf
  • 23+54+16+.docx
  • 09+29+00.pdf
  • 00+80+05+%28wo_markup%29.pdf
  • 23+64+26.docx
  • SiteUtilities.pdf
  • 07+84+00.pdf
  • 32+12+10.1.docx
  • 00+71+00+%28wo_markup%29.pdf
  • 23+82+01.docx
  • 32+01+16.pdf
  • 22+00+00.pdf
  • 07+19+00.pdf
  • 06+61+16.pdf
  • B3707+High+Bay+East+Wall.jpg
  • 32+92+23.pdf
  • afman91-203_oc-alcsup.pdf
  • 180061-Final+Plan+Set+REV_2.pdf
  • tinkerafbi13-204.pdf
  • 01+32+16.00+20+%28wo_markup%29.pdf
  • 23+25+00.pdf
  • 32+12+10.1.pdf
  • 07+21+16.pdf
  • 23+70+03.pdf
  • Readme_Editable+versions+Not+in+this+Directory.txt
  • 32+01+13.pdf
  • 32+31+13.pdf
  • 23+23+00.docx
  • 40+17+26.00+20.pdf
  • 32+01+16.docx
  • Section+L+-+Instructions+to+Bidders+%282-Step%29.pdf
  • 32+11+29.docx
  • 007200_Attch+13_AF487.pdf
  • 08+11+13.pdf
  • site+visit+sign+in.pdf
  • 21+13+17.pdf
  • 06+10+00.pdf
  • 00+72+00.pdf
  • 31+23+16.docx
  • ufc_3_600_01_2016_c6.pdf
  • 10+22+39.pdf
  • 23+36+00.00+40.pdf
  • 07+54+19.pdf
  • tinkerafb_HWMP.pdf
  • 007200_Attch+14_Information+for+New+Boilers.pdf
  • TABLE+OF+CONTENTS.docx
  • 07+12+00.pdf
  • 23+08+00.docx
  • SOW_Att_4_180061_Design+Narrative+v2.pdf
  • 03+39+00.00+10.pdf
  • 08+34+01.pdf
  • 23+08+01.00+20.pdf
  • 32+13+14.docx
  • 01+78+00+%28wo_markup%29.pdf
  • 09+65+00.pdf
  • WWYK180061+-+Pre-Bid+RFI+2nd+Response+COR.pdf
  • 180061+-+Pre-Bid+RFIs+-+28+Aug+25+signed.pdf
  • 180061+-+Pre-Bid+RFIs+-+28+Aug+25+-+User+response+-+Combined.pdf
  • 180061+-+Pre-Bid+RFIs+-+15+Sep+25+-+GK.pdf
  • WWYK180061+Repair+HVAC+B3707+RFI+004+Clarification+Request+GK.pdf