Z1DA--578-25-003 Renovate Elevators B200 (Construction) at the Hines VA Hospital in Hines, IL
SAM.GOV
Due: August 21, 2025 at 05:00 AM UTC
Active
Solicitation SDVOSBC Source Url

Summary

The opportunity Z1DA--578-25-003 involves the renovation of elevators in Building 200 at the Hines VA Hospital in Hines, Illinois. This construction project aims to replace five passenger elevators and three service elevators that are currently in poor condition and nearing the end of their useful life. The work is critical to improving the efficiency and reliability of elevator services for patients and staff, as the existing elevators are failing more frequently and are difficult to repair due to a lack of available parts. Contractors with experience in elevator installation and renovation, particularly those who are Service-Disabled Veteran-Owned Small Businesses (SDVOSB), are encouraged to bid on this project, as it is set aside for such businesses under FAR 19.14.
Description

Amendment 0001: 578-25-003 Renovate Elevators 
B200

Entities
VADO
Department of Veterans Affairs
NAICS
238290
Set Aside
SDVOSBC : Service-Disabled Veteran-Owned Small Business Set Aside
Place of Performance
Hines , Illinois 60141
Point of Contact
Full Name Email Phone Type
Kristi Kluck [email protected] 414-844-4879 primary
Attachments
  • 36C25225R0036_3.docx
  • S02+Sol+R0036+AttA+VAAR+852.219-75+Certification+578-25-003.docx
  • S02+Sol+R0036+AttC+Contractor+EMR+Safety+Info+578-25-003.docx
  • S02+Sol+R0036+AttE+SOW.Att00_Descriptive+Project+Scope+of+Work+578-25-003_r.pdf
  • S02+Sol+R0036+AttE+SOW.Att15d_578-25-003+100+perc+DWGS+Part+4of5_2025.01.24.pdf
  • S02+Sol+R0036+AttE+SOW.Att12_Cutting+Welding+and+Other+Hot+Work.pdf
  • S02+Sol+R0036+AttE+SOW.Att18b_Building+220+Colored+Space+Drawings.pdf
  • S02+Sol+R0036+AttB+Contractor+Info+578-25-003.docx
  • S02+Sol+R0036+AttE+SOW.Att09_Infection+Control+Risk+Assessment_ICRA-1.3.pdf
  • S02+Sol+R0036+AttE+SOW.Att14a+_578-25-003_Replace+Elevators+B200_SPECS+VOL+1of+2_updated.pdf
  • S02+Sol+R0036+AttE+SOW.Att07_Pre-Construction+Risk+Assessment_PCRA+1.1.pdf
  • S02+Sol+R0036+AttG+Brand+Name+or+Equal_Basis+of+Design+578-25-003.xlsx
  • S02+Sol+R0036+AttE+SOW.Att04_No+Smoking+Policy+10-1-19.pdf
  • S02+Sol+R0036+AttE+SOW.Att06_Pre-Construction+Checklist.pdf
  • S02+Sol+R0036+AttE+SOW.Att13_OIT+Horizontal+Cable+Requirements.pdf
  • S02+Sol+R0036+AttE+SOW.Att05_Safety+and+Health+During+Construction+Activities.pdf
  • S02+Sol+R0036+AttE+SOW.Att03_Emergency+Contact+List.pdf
  • S02+Sol+R0036+AttE+SOW.Att15a_578-25-003+100+perc+DWGS_Part+1of5_2025.01.24.pdf
  • S02+Sol+R0036+AttE+SOW.Att01_Contractor+Badging_Fingerprint+Request+Form+2025.pdf
  • S02+Sol+R0036+AttI+Wage+Rates+IL20250009.R3+2025.05.23+current+as+of+2025.06.05.pdf
  • S02+Sol+R0036+AttF+SOW.Att19_Subcontractor+Info+Consent+578-25-003.pdf
  • S02+Sol+R0036+AttH+Past+Performance+Client+Questionnaire+578-25-003.pdf
  • S02+Sol+R0036+AttE+SOW.Att08_Interim+Life+Safety+Measures_ILSM.pdf
  • S02+Sol+R0036+AttE+SOW.Att15e_578-25-003+100+perc+DWGS+Part+5of5_2025.01.24.pdf
  • S02+Sol+R0036+AttD+Financial+Disclosure+578-25-003.docx
  • S02+Sol+R0036+AttE+SOW.Att11_Above+Ceiling+Entry+and+Wall+Construction+Permits.pdf
  • S02+Sol+R0036+AttE+SOW.Att15c_578-25-003+100+perc+DWGS+Part+3of5_2025.01.24.pdf
  • S02+Sol+R0036+AttE+SOW.Att16_578-25-003+Basis+of+Design+Existing+Condition+Photos+2024.11.04.pdf
  • S02+Sol+R0036+AttE+SOW.Att14b+_578-25-003_Replace+Elevators+B200_SPECS+VOL+2of+2_updated.pdf
  • S02+Sol+R0036+AttE+SOW.Att15b_578-25-003+100+perc+DWGS_Part+2of5+2025.01.24.pdf
  • S02+Sol+R0036+AttE+SOW.Att17_Building+200+Elevator+Study+Existing+Condition+Photos.pdf
  • S02+Sol+R0036+AttE+SOW.Att18a_Building+200+Colored+Space+Drawings.pdf
  • S02+Sol+R0036+AttE+SOW.Att02_Contractor+Parking.pdf
  • S02+Sol+R0036+AttE+SOW.Att10_Infection+Control+Barrier+Sample.pdf
  • S06+001+Att1+Sign-in+Site+Visit_01+for+578-25-003+Elevators+2025.06.18.pdf
  • 36C25225R0036+0001.docx
  • S06+36C25225R0036+002+Att2+Sign-in+Site+Visit_02.pdf
  • S06+36C25225R0036+002+Att1+Sign-in+Site+Visit_01.pdf
  • S06+36C25225R0036+002+578-25-003.docx
  • S06+36C25225R0036+003+Att2+Sign-in+Site+Visit_02_rev.pdf
  • 36C25225R0036+0003.docx
  • S06+36C25225R0036+003+Att1+Sign-in+Site+Visit_01.pdf
  • S06+36C25225R0036+004+578-25-003_Att+Finish+Schedule.pdf
  • 36C25225R0036+0004.docx
  • S06+36C25225R0036+0005.docx
  • S06+36C25225R0036+0005.pdf
  • S06+36C25225R0036+006_Att02+25-0725+Supplemental+Sketches.pdf
  • BLDG200F13R2010.xls
  • S06+36C25225R0036+006_Att07+26+22+00+Low-Voltage+Transformers.pdf
  • BLDG200F3R2010.xls
  • S06+36C25225R0036+006_Att05+Physical+Access+Control+Clarifications.pdf
  • S06+36C25225R0036+006_Att12+Sole+Source+Listing__full.e.pdf
  • S06+36C25225R0036+006_Att06+26+43+13+Surge+Protection+Devices+-+Addendum+1.pdf
  • BLDG200F7R2010.xls
  • S06+36C25225R0036+006_Att11+Photos_Existing+Conditions.pdf
  • BLDG200F6R2010.xls
  • S06+36C25225R0036+006_Att01+Finish+and+Lighting+Changes.pdf
  • BLDG200+F10R2010.xls
  • S06+36C25225R0036+006_Att09+Hines+State+Tax+Exempt+2025.pdf
  • BLDG200F4R2010.xls
  • BLDG200F11R2010.xls
  • BLDG200F9R2010.xls
  • BLDG200BSMTR2010.xls
  • S06+36C25225R0036+006_Att10+OFFER+SCHEDULE.R1+578-25-003+B200+Elevators.pdf
  • BLDG200F2R2010.xls
  • BLDG200F1R2010.xls
  • S06+36C25225R0036+006_Att08+GKT15-30W-10_Specification.pdf
  • BLDG200F8R2010.xls
  • S06+36C25225R0036+006_Att04+_+Wage+Rates+IL20250009.R3+2025.08.01.pdf
  • BLDG200F14R2010.xls
  • BLDG200F5R2010.xls
  • 36C25225R0036+0006.docx
  • 36C25225R0036+0007.docx